Construction Claims Monthly

 
2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | 2001 | 2000 | 1999 | 1998 | 1997 | 1996 |

Searched Library for year - 2005
 

December 2005 - Volume 27 Number 12

Financial Data Not Consistent With Eichleay Formula Delay-damages; Overhead
Subcontractor Punished For Payment Deal Subcontractors; Payment
No Jurisdiction Over Breserve1-rigging Claim Breserve1s; Subcontractors
Default Termination Upheld Termination-default
Breserve1 Responsive Despite Lack Of Acknowledgment Breserve1s-responsiveness; Breserve1s-solicitati
Power Of Attorney Form Rendered Breserve1 Bond Defective Bonds-breserve1; Breserve1s-responsiveness
Certification Dreserve1 Not Cover Additional Claim Claims Administration; Subcontractors
Notice Of Damage By Separate Prime Was Insufficient Multiple Prime Contracts; Notice
Who Finances Extra Work?
Construction Manager May Be Agent Of Owner Multiple Prime Contracts; Payment
"Pay-if-pareserve1" Clause Dreserve1 Not Shift Risk Of Nonpayment Condition Precedent; Payment
Termination Settlement Proposal Not Timely Termination-convenience
Request For Adjustment Was Not A "Claim" Claims Administration
Government Time Credit Includes Price Credit Changes-deductive
Contractor Misrepresented Excavation Quantities Payment; Unit Prices
Reciprocal Waiver Survives Breach Of Contract Insurance; Waiver
Breserve1 Approval Rescinded Due To Omitted Clauses Breserve1s-solicitations

INDEX


November 2005 - Volume 27 Number 11

Disclaimer Barred Sequencing Claim Delay-damages; Disclaimers
Lack Of Lien Waivers Precluded Final Payment Liens; Waiver; Substantial Completion
Work Not Constructively Accelerated Acceleration; Delay-excusable
No Deductive Credit For Reduced Bond Premium Changes-deductive; Bonds
Preparation Time Ruled Reasonable Breserve1s-solicitations
Contractor Bound By Surety's Litigation Bonds-payment; Indemnification
Court Asks If Construction Defects Are "Property Damage" Insurance; Workmanship
When Is A Project Substantially Complete?
No Reason To Suspect Breserve1 Mistake Breserve1s-mistakes; Subcontractors
Pricing Information Ruled Trade Secret Suppliers
"Match"Does Not Require Exact Duplication Plans And Specifications
Government Liable For Misdirected Eft Payment Payment-progress
Earlier Contracts Not Consreserve1ered Breserve1s
No Substantial Completion Of Tenant Improvements Substantial Completion
Payment Surety Bound By Joint Check Agreement Bonds-payment; Suppliers

October 2005 - Volume 27 Number 10

General Release Applied To Existing Claims Release; Claims Administration
Wrongful Termination Extinguished Arbitration Arbitration; Waiver; Termination
Owner Pays Dearly For Wrongful Termination Termination-default; Damages
"Responsible Breserve1der" Status Is Not Protected Property Breserve1s-responsibility
No Breserve1 Correction After Contract Award Breserve1s-mistakes; Equitable Relief
Reciprocal Waiver Barred Suit Against Contractor Insurance; Waiver
"No Less Than" Is Not A "Sum Certain" Claims Administration
Project Owner Warranty Of Site Access
Owner Liable For Unrecorded Utility Lines Differing Site Conditions-subsurface
No Administrative Fee On Cost-plus Contract Overhead
Board Applies "Total Cost" Method Estimates; Claims Administration
Board Will Not Duplicate Pending Litigation Claims Administration
Attorney Fees Recovered In Excess Of Cap Breserve1s-protests; Attorney Fees
Expired Lien Mandated Release Of Retainage Liens; Retainage
No Antitrust Recovery For Undercut Breserve1s Breserve1s; Damages

September 2005 - Volume 27 Number 9

Contractor Liable To Sub For Failure To Field Verify Plans And Specifications; Inspection
Florreserve1a Restricts Eichleay Recovery Delay-damages; Overhead
Handling Of Stockpiled Materials Was Not Extra Work Changes-constructive
Contractor Mishandled Hybrreserve1 Specifications Plans And Specifications
Contractor Recovers For Wrongful Termination Termination-default; Damages; Profit
Owner's Nonpayment Dreserve1 Not Involve Retainage Retainage; Attorney Fees
Recovery For Idled Equipment
Last Minute Lien Was Not Economic Duress Liens
Implied Warranty Extended To Subsequent Purchasers Warranty-implied; Workmanship
Contractor Achieves Partial Remission Of Liqureserve1ated Damages Liqureserve1ated Damages; Inspecti
Price Revisions Mandated Schedule Revisions Breserve1s; Schedule
Proposal Lacked Sufficient Technical Detail Breserve1s-responsiveness
Claims Board Not Limited By Appropriations Claims Administration
Sub's Pay Measurement Ruled More Accurate Unit Prices; Claims Administration

August 2005 - Volume 27 Number 8

Florida High Court Addresses Payment Bond Notice Bonds-payment; Notice
Upward Correction Of Low Bid Allowed Bids-mistakes
Contractor Denied Cost Of Defending Payment Claim Attorney Fees; Bonds-payment
Quality Control Directive Was Not A Change Changes-constructive
Gao Had Protest Jurisdiction Over Hybrid Contract Bids-protests
Jilted Subcontractor Recovers Lost Profit Subcontractors; Profit
Prequalification Protest Not Timely Bids-protests
Surety Can Settle Claims Without Consent Bonds-performance; Indemnification
Total Cost Delay Claims
California High Court Clarifies Licensing Law Licenses; Payment
Forfeiture Of Bid Security Ruled Improper Bids-mistake; Bonds-bid
Contractor Recovers For Constructive Acceleration Schedule; Acceleration
Partial Fee Recovery Based Upon
Solicitation Cancelled Due To Price Confusion Bids-solicitations; Unit Prices
Court Interprets
Owner Used Improper Bid Evaluation Factor Bids-responsiveness

July 2005 - Volume 27 Number 7

Contract Award Cancelled Prior To Signing Bids
State Wage Statute Supplemented Davis-bacon Regulations
Unamortized Costs Recovered After Termination Termination-convenience
Pay Measurement Excluded Certain Fill Unit Prices; Payment
Bid Protester Awarded Costs Bids-protests; Attorney Fees
Bid Protester Denied Costs Bids-protests; Attorney Fees
Limitation Clause Applied Only To Late Completion Disclaimers; Liquidated Damages
Bid Rejected Due To License Number Problems Bids-responsiveness; Licenses
Liens As Security For Arbitration Awards
Pay-if-paid"Clause Defeats Payment Bond Rights Subcontractors; Bonds-payment
Florida Court Modifies Eichleay Rule Delay-damages; Overhead
Loss Ratio Applied To Termination Settlement Termination-convenience
Reliance On Project Limits Not Reasonable Plans And Specifications; Changes-constructive
Delay Not Included In Prior Contract Modification Claims Administration
Subcontractor Not Held To Pre-bid Price Quotation Bids; Subcontractors; Equitable Relief
Lien Filing Did Not Waive Arbitration Rights Arbitration; Waiver; Liens
Arbitration Clause Ruled Unconscionable Arbitration

June 2005 - Volume 27 Number 6

Contractor Responsible For Pre-bid Soil Investigation Differing Site Conditions-subsurface
Subcontracting Preferences Struck Down Regulations; Subcontractors
Government's "Reverse-delay" Claim Denied Changes-deductive
Cost Should Have Been Included In Base Scope Unit Prices
Contractor Not Obligated To Prosecute Sub's Claim Claims Administration; Subcontractors
Altered Contract Did Not Call For Arbitration Arbitration
Establishing The Amount Of Liquidated Damages
Prompt Payment Act Applied Only To Retainage Retainage; Payment-final
Acceleration Claim Barred By Lack Of Notice Acceleration; Notice
Contractor's Early Completion Claim Denied Schedule; Interference
Proposal Downgraded In Accordance With Criteria Bids
Superior Experience Prevails Bids
Construction Manager Liable To Injured Worker Multiple Prime Contracts; Safety
Sub Terminated Unjustly For Lack Of Progress Schedule; Termination-default

May 2005 - Volume 27 Number 5

Supplier To Second-tier Sub Recovers Against Bond Bonds-payment; Suppliers
Bidder Recovers Lost Profit From City Bids-protests; Profit
Drawing Narrowed Spec But Did Not Conflict Plans And Specifications; Changes-constructive
Contractor Could Have Avoided Spatial Conflicts Coordination; Shop Drawings
Amendment Did Not Impose Additional Requirements Bids-responsiveness
Owner Shifted Subsurface Risk To Contractor Differing Site Conditions-subsurface; Disclaimers
Change Order Requirement Waived At Meetings Changes-directed; Waiver
Disappointed Bidder Recovery Of Lost Profit
Contractor Sues Cm Over Master Schedule Schedule; Negligence
Subordination Of Liens Not Enforced Liens; Project Financing
Proprietary Specification Enforced Plans And Specifications; Delay-compensable
Solicitation And Master Specs Interpreted Plans And Specifications
Acknowledgment Did Not Cure Obsolete Bid Schedule Bids-responsiveness
Missing Waivers Did Not Justify Forfeiture Of Retainage Retainage; Waiver; Delay-excusable
Owner Had Actual Knowledge Of Extra Work Changes-directed; Changes-constructive

April 2005 - Volume 27 Number 4

Mechanic's Lien On Condos Had To Be Apportioned Liens
Default Was Exception To "Pay-if-paid" Clause Payment-final; Subcontractors
Cpm Analysis Needed To Establish Shop Drawing Delay Delay-compensable; Schedule; Shop Drawings
Omission Of Clauses Not Determinative Bonds-payment
Proposal Properly Downgraded Bids
Design/Supply Contract Subject To Competitive Bidding Bids; Suppliers
New York Court Enforces Clause Under Florida Law Payment-final; Subcontractors
Change Order Work Was Unit Priced Unit Prices; Acceptance
Weather And Excusable Delay
Addendum Acknowledged Despite Missing Signature Bids-responsiveness
Contractor Gave Supervisor "Apparent Authority" Changes-directed
Long Distance Documents Had To Be Examined Differing Site Conditions-subsurface
No Postponement Of Notice-to-proceed Delay-nonexcusable
Id/Iq Contracts Did Not Shift Unreasonable Risk Bids-solicitations
Contractor Absorbs Subcontract Price Increase Changes-directed; Subcontractors
Supplier Did Not Breach Technical Support Obligation Suppliers

March 2005 - Volume 27 Number 3

Prompt Payment Act Applied Only To Progress Payments Payment; Attorney Fees
Lack Of Site Inspection Not Fatal To Spec Claim Inspection-pre-bid; Plans And Specifications
Contractor Failed To Establish "Equal" Product Plans And Specifications; Shop Drawings
Amendment Did Not Supersede Military Spec Bids-solicitations; Plans And Specifications
Disclosure Restriction Ruins Bid Bids-responsiveness
Agency Took Prompt Remedial Action Bids-protests
Change Order Requests Were Not "Claims" Claims Administration; Payment-final
False Claims Penalty Assessed By Arbitrator Arbitration
A/E Liability For Negligent Misrepresentation
Mechanic's Lien Ruled Constitutional Liens
Contractor Pursues Architect For Misrepresentation Architects And Engineers; Negligence
Deficient Work Not Specifically Referenced Termination-default
Default Justified By Inadequate Lead Abatement Termination-default
State Law Determines Corporate Standing Claims Administration
Assignee Allowed To Recover Against Payment Bond Bonds-payment; Subcontractors
Purchase Order Did Not Govern Transaction Suppliers; Schedule

February 2005 - Volume 27 Number 2

License Required For Protection Of Limitation Statute Statutes Of Limitation; Licenses
Delay Disclaimer Not Voided By Statute Delay-damages; Disclaimers
Concurrent Delay Subsumed By Contract Modification Delay-compensable; Release
Prime Allowed To Sponsor Subcontractor Claim Claims Administration; Subcontractors
Mutually Exclusive Options Included In Evaluation Bids-solicitations
Descriptive Literature Required To Support "Equal" Product Bids-responsiveness; Plans And Specificat
Lien Included Change Order Profit But Not Interest Liens; Profit; Interest
Cost Sharing Survived Convenience Termination Termination-convenience
Withdrawal Of Mistaken Bids
Below-cost Bid Was Not False Claims Violation Bids; Estimates
Owner Not Protected By "No Lien" Clause Liens; Waiver
Design Responsibilities Included Renovation Changes-constructive
Design Did Not Provide Adequate Space Plans And Specifications; Coordination
Additional Components Did Not Force Redesign Changes-constructive
Sub Could Be Held To Quote Despite Known Mistake Bids-mistakes; Equitable Relief
Payment Withheld Due To Unresolved Claims Payment-final; Interest
Bid Nonresponsive Due To Inadequate Subcontracting Efforts Bids-responsiveness; Subcontractors

January 2005 - Volume 27 Number 1

Unlicensed Sub Recovers For Unjust Enrichment Licenses; Payment
Payment Bond Not Limited On Indefinite-quantity Contract Bonds-payment
Defective Final Decision Dreserve1 Not Trigger Appeal Period Claims Administration
Board Had No Authority To Impose Monetary Sanctions Claims Administration; Attorney Fees
Qualification Spoiled Fixed-price Quotations Breserve1s
Prime's Decision Became Binding On Sub Claims Administration; Arbitration
Employee Trust Fund Allowed To Lien Project Liens
No Conflict Between Specification And Special Provision Plans And Specifications; Changes-constructi
Owner Liability For Delay Of Separate Contractors
Sequential Delay Dreserve1 Not Annul Liqureserve1ated Damages Delay-excusable; Liqureserve1ated Dama
Warranty Exclusion Was Nonresponsive Breserve1s-responsiveness; Warranty-express
Construction Standards Imposed Work Requirements Plans And Specifications; Changes-constructive
Substantial Justification Based On Overall Dispute Attorney Fees
Deadline Enforced For Proposal Revision Breserve1s
Board Of Claims Could Not Bring In Construction Manager Multiple Prime Contracts; Claims Administrat
Update On Washington Breserve1 Shopping Statute

×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team