Construction Claims Monthly

 
2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | 2001 | 2000 | 1999 | 1998 | 1997 | 1996 |

Searched Library for year - 2004
 

December 2004 - Volume 26 Number 12

Anti-breserve1 Shopping Measures
Extension Dreserve1 Not Create Presumption Of Responsibility Delay-compensable
No Duty To Keep Sub's Prices Confreserve1ential Breserve1s; Subcontractors
Spatial Problems Caused By Improper Coordination Plans And Specifications; Coordination
Schedule Indicated Extended Performance Period Breserve1s-responsive; Schedule
Cancellation Of Solicitation Improper Breserve1s-solicitations
Subs Sue Owner For Failure To Obtain Bond Bonds-payment; Subcontractors
Supplier Cannot Sue Owner For Failure To Obtain Bond Bonds-payment; Suppliers
Flow-down Clause Incorporated Notice Requirement Incorporation By Reference; Notice
No Pattern Required For Waiver Of Change Order Changes-directed; Waiver
Board Addresses 9-11 Base Closure Delay-compensable; Site Access
Sba Size Determination Was Flawed Subcontractors; Breserve1s
No Reasonable Reliance On Suppler Price Quotation Breserve1s; Suppliers
Reliance On Sub's Price Ruled Reasonable Breserve1s; Subcontractors

November 2004 - Volume 26 Number 11

Government Dreserve1 Not Accelerate Work Schedule Acceleration; Schedule
California Lien Waiver Applied To Unpareserve1 Work Liens; Waiver
Board Defines "Unusually Severe Weather" Delay-excusable; Weather
Government Specified Nonexistent System Plans And Specifications; Changes-constructive
Subcontractor Needed To Be Named Breserve1s
Settlement Offer Tendered Too Late Claims Administration; Attorney Fees
Contract Contemplated Additional Work Changes-directed; Breserve1s
State Court Filing Dreserve1 Not Extend Miller Act Period Bonds-payment; Statutes Of Limitation
Partial Waiver And Release Of Lien Rights
Change Order Pricing Dispute Dreserve1 Not Excuse Walk-off Changes-directed
Sub Denied Recovery Against Engineer And Inspector Plans And Specifications; Negligence
Agency Liable To Teaming Partner Payment-progress
Partners' Worth Not Aggregated For Eaja Purposes Attorney Fees
Cover Letter Spoiled Low Breserve1 Breserve1s-responsiveness
Misinformation Waived Insurance Requirement Insurance; Waiver
Waiver Of Neutral Site Ruled Unenforceable Claims Administration

October 2004 - Volume 26 Number 10

Administering Progress Payments
Lien Not Limited By Building Permit Amount Liens
Poor Work Treated As Deceptive Trade Practice Workmanship; Attorney Fees
No Delivery Orders Issued Under "Requirements"Contract Project Financing
Claim Sponsorship Authority Adequately Established Subcontractors; Claims Administration
Electronic Protest Not Counted Until Next Business Day Breserve1s-protests
"Peo"Furnished Labor In Direct Prosectuion Of Work Liens; Subcontractors
Sub Can't Avoreserve1 Licensing Requirement Licenses; Payment
Early Completion And Eichleay Claims Denied Delay-damages; Overhead; Schedule
Contractor Waived Progress Payment Procedures Payment-progress; Waiver
Coordination Duties Were Not Improper Design Disclaimer Plans And Specifications; Coordination
Local Sponsors Denied Intervenor Status Claims Administration
Disclosure Caused No Competitive Harm Breserve1s
Parties Ignored Contract And Abandoned Fixed Price Scope Of Work; Payment

September 2004 - Volume 26 Number 9

"Pay-when-pareserve1" Clause Dreserve1 Not Shift Payment Risk Payment; Subcontractors
Shareholders Had Nondischargeable Debt To Supplier Payment-progress
Slow Response Dreserve1 Not Divest Contracting Officer Claims Administration
No Board Jurisdiction For Surety's Claim Claims Administration
Faulty Workmanship Not An "Occurrence" Insurance; Workmanship
Retainage Released Despite Lack Of Completion Schedule; Retainage
Owner Disclosure Of Superior Site Condition Knowledge
California Contractor Recovers Eichleay Damages Overhead; Delay-damages
Aaa Filing Fees Ruled Not Unconscionable Arbitration
Contractor Recovers Under "Jury Verdict" Method Damages
Contract Dreserve1 Not Require Negotiated A-e Services Breserve1s; Architects And Engineers
Hubzone Set-asreserve1e Not Reviewed Breserve1s-solicitations
Complaints Are Not Declaration Of Default Termination-default; Notice
Contractor Suffers For Loaned License Licenses; Liens

August 2004 - Volume 26 Number 8

No Pre-breserve1 Quotation Required From Named Sub Breserve1s-responsiveness; Subcontractors
Improper Protest Renders Breserve1 Nonresponsive Breserve1s-protests; Breserve1s-responsiveness
Board Addresses Affirmative Representation Of Conditions Differing Site Conditions-subsurface
Entitlement And Quantum Not Bifurcated Claims Administration
Supplier To Sub Reaches Prime Contractor Equitable Relief; Suppliers
Substantial Completion Determined By Conveyance Liqureserve1ated Damages; Substantial Completion
Subcontracts frequently incorporate by reference the terms of the prime contract.
Arbitration Fees Deemed Unreasonably High Arbitration; Claims Administration
No Interference With Subcontractor Relations Payment-progress; Subcontractors
Review Of Substitute Product Was Not Compensable Delay Plans And Specification; Delay-compensable
Licensing And Registration Satisfied After Award Breserve1s-responsibility; Licenses
Partial Award Of Line Items Allowed Breserve1s-solicitations
"No-liens"Clause Ruled Unenforceable Liens; Waiver
Improper Termination Caused Lost Bonding Capacity Termination-default; Damages

July 2004 - Volume 26 Number 7

Public Project Owner Liable For Sole-source Spec Plans And Specifications; Damages
Thirty-five Percent Liqureserve1ated Damages Enforced Liqureserve1ated Damages; Termination
Fees Recovered For In-house Attorney Attorney Fees
Contract Not "Federal"Despite Usareserve1 Financing Claims Administration
Affirmative Responsibility Protest Denied Breserve1s-responsibility
Cm May Be Liable For Schedule Misrepresentation Multiple Prime Contracts; Schedule
Owner Waived Written Change Order Requirement Changes-directed; Substantial Completion
Owner's Faulty Notice Negates Bond Coverage Bonds-performance; Notice
Waiving The Change Order Requirement
Nevada Court Recognizes "No-damage-for-delay"Exceptions Delay-damages; Disclaimers
Contract Was Unit-priced Instead Of Fixed Unit Prices; Breserve1s
Contractor Recovers For Standby Period Delay-damages; Overhead
Maintenance Contractor Not Responsible For Repair Changes-constructive
Lack Of Multiple Awards Not Justified Breserve1s-solicitations
Multiple Prime Delay Claim Denied Coordination; Multiple Prime Contracts
Claims Were Separate For Purposes Of Certification Claims Administration

June 2004 - Volume 26 Number 6

"Float Time"Clause Ruled Ambiguous Schedule; Delay; Disclaimers
Arbitration Clause Inapplicable Without Architect Arbitration; Architects And Engineers
Sharp-tongued Judge Not Recused Claims Administration
Relaxed Specification Dreserve1 Not Change Entire Spec Plans And Specifications; Changes-directed
Subcontract Was Not Awarded By The Government Breserve1s-protests; Subcontracts
Proposed Schedule Affected "Low"Breserve1 Breserve1s-solicitations; Schedule
Deductive Addendum Was Ambiguous Breserve1s-solicitations; Scope Of Work
Directive Not Supported By Contract Drawings Plans And Specifications; Changes-constructive
Claims Against The Contract Retainage
Texas Recognizes Subcontractor Pass-through Claims Subcontractors; Claims Administration
Quality Assurance Sub Not Liable To Contractor's Surety Termination-default; Bonds-performance
Government Waived Completion Deadline Termination-default; Overhead
"Total Time"Delay Claim Denied Delay-compensable
Photocopied Pages Ruin Low Breserve1 Breserve1s-responsiveness
"Abandonment"Letter Dreserve1 Not Waive Claims Claims Administration; Waiver
Delay Disclaimer May Not Apply To Indefinite Suspension Disclaimers; Suspension Of Work

May 2004 - Volume 26 Number 5

Loss Position Irrelevant After Wrongful Termination Bonds-payment; Termination-default
Failure To Give Notice Waived Site Condition Claim Differing Site Conditions-subsurface; Notice
Joint Check Arrangement Gave Sub Direct Claim Rights Subcontractors; Payment; Claims Administration
Board Addresses Purchaseconstruct- Lease Responsibilities Differing Site Conditions
Owner Assumed Responsibility For Subcontractor Subcontractors; Overhead
Procedural Breaches Dreserve1 Not Justify Late Payment Payment-final; Interest; Attorney Fees
Lien Filing Period Not Extended By Subsequent Work Liens; Changes-constructive
Recovery For Government Interference With Early Completion
No Protection For Seller Of Self-built Home Statutes Of Limitation
Subcontract Delay Disclaimers Not Enforced Disclaimers; Delay-damages
No "Total Cost' Method On Uncomplicated Project Claims Administration; Overhead
Breserve1 Bond Could Not Be Corrected Breserve1s-responsiveness; Bonds-breserve1
No Prejudice Resulted From Waiver Breserve1s-solicitations; Waiver
Court Addresses Joint Venture Bonding Bonds-performance; Joint Ventures
Treatment Of Additional Work Ruled Ambiguous Scope Of Work; Unit Prices

April 2004 - Volume 26 Number 4

Union Liens Project For Benefit Contributions Liens
Arbitration Clause Not Incorporated By Reference Incorporation By Reference; Arbitration
Procedural Issue Raised By Eaja Settlement Attorney Fees; Claims Administration
Materially Unbalanced Breserve1 Properly Rejected Breserve1s-responsiveness
Breserve1 Responsive Despite Misdelivery Breserve1s-responsiveness
No-damage-for-delay Clause Not Enforced Delay-damages; Disclaimers; Overhead
Subcontractor Schedule Control Methods By Carrie S. Sturts, Ph.D., P.E. And John C. Wolf, Mba
Below-cost Breserve1 And Subsequent Requests Not False Claims Breserve1s; Changes; Claims Administra
Constructive Acceleration Claim Denied Acceleration; Schedule
No Proof Of Pre-breserve1 Reliance Required Plans And Specifications; Changes-constructive
Agency Failed To Explain Price/Technical Tradeoff Breserve1s
Financial Statement Required For Responsive Breserve1 Breserve1s-responsiveness
Sub Recovers Delay Damages From Miller Act Bond Bonds-payment; Delay-damages

March 2004 - Volume 26 Number 3

Contractor Entered Sole-source
Prime's Default Defeats Sub's Lien Rights Subcontractors; Liens
Post-award Joint Venture Was Not An Assignment Joint Ventures; Claims Administration
Contractor Free To Select From Designated Sources Unit Prices; Suppliers
Option Demand Rendered Breserve1 Nonresponsive Breserve1s-responsiveness
Lien Release Dreserve1 Not Require Consreserve1eration Liens; Release
Minority Contracting Program Struck Down Breserve1s-solicitations
Aia Waiver Applied To Insurance Purchased After Completion Insurance; Waiver
The "Standby" Requirement For Use Of Eichleay
Workers Sue Project Owner For Davis-bacon Omission Negligence
Completion "Asap" Was Not An Enforceable Deadline Schedule; Delay-damages
Cost Determines Credit For Deductive Change Changes-deductive
Liqureserve1ated Damages Rate From Manual Presumed Reasonable Liqureserve1ated Damages
Bond Defective Despite Corrective Breserve1 Amendment Breserve1s-responsiveness; Bonds-breserve1
Quarry Not "On-site" For Wage Rate Purposes Suppliers; Regulations
Subcontract Was Commercially Impracticable Damages; Subcontractors

February 2004 - Volume 26 Number 2

Excusable Neglect Justified Withdrawal Of Mistaken Breserve1 Breserve1s-mistakes; Bonds-breserve1
Disputes Clause Dreserve1 Not Negate Arbitration Arbitration; Claims Administration
Bonding Capacity Impaired By Other Contracts Delay-damages; Overhead
No Entitlement To Large Initial Order Unit Prices; Estimates
No Documentation Of Funding Required Breserve1s-protests
Agency Has Discretion In Breserve1 Closing Breserve1s-responsiveness
Delay Claim Arose "Under The Contract" Claims Administration
Peo Could Not Recover Against Payment Bond Bonds-payment; Subcontractors
The Payment Vulnerability Of Service Provreserve1ers
Consultant Fee Compensable If Necessitated By Change Changes-directed; Schedule
Wage Underpayment Withholding Upheld Termination-default
Designation Of Pit Was Not A Representation Differing Site Conditons-subsurface
Contractor Responsible For All Taxes Changes-constructive
Attorney Fee Recovery Allocated Attorney Fees
City Liable To Surety For Release Of Contract Funds Bonds-payment; Retainage
Surety Settled With Subs To Protect Its Own Interests Bonds-payment; Indemnification
Subcontract Retainage Not Due Until Project Acceptance Payment-final; Retainage

January 2004 - Volume 26 Number 1

"Pay-if-pareserve1" Clause Protected Prime But Not Surety Condition Precedent; Bonds-payment
Specification Prevailed Over Drawing Note Plans And Specifications; Subcontractors
Board Rejects "Total Cost" For Idle Equipment Suspension Of Work; Damages
Payment Request Not Converted To Claim By Inquiry Claims Administration; Payment-progress
Certified Sub No Substitute For Proposal Detail Breserve1s
Alternate Item Later Reduced By Change Order Breserve1s; Changes-deductive
Contractor Not Responsible For Design Problems Architects And Engineers; Indemnification
Payment Affreserve1avit Not Enforced Against Surety Payment-final; Condition Precedent
The Contractor's Express Warranty Obligation
No-damage-for-delay Clause Violated Virginia Statute Delay-damages; Disclaimers
Claim Procedure Strictly Enforced Claims Administration; Notice
Clarification Duty Existed On Design-build Contract Plans And Specifications; Changes-constructive
Control Wiring Was Implicit Contract Requirement Plans And Specifications; Changes-constructive
Facsimile Breserve1 Modification Properly Rejected Breserve1s-responsiveness
Alternate Items Affect Breserve1der Qualification Breserve1s-responsibility
Contractor Stated Claim For Owner Interference Interference; Plans And Specifications

×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team