Construction Claims Monthly

 
2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | 2001 | 2000 | 1999 | 1998 | 1997 | 1996 |

Searched Library for year - 2000
 

December 2000 - Volume 22 Number 12

Contractor Defaulted For Failure To Provreserve1e Assurance Termination-default; Schedule
Owner Not Protected By Delay Disclaimer Delay-damages; Disclaimers
Likelihood Of Completion Methodology Upheld Termination-default; Schedule Appeal Of Thomas & Sons, I
No Disruption Of Cash-flow - Unabsorbed Overhead Denied Overhead; Delay-damages Young Enterprises Of
Registration For E-mail Notices Essential Breserve1s-solicitations
Response To Database Must Be Prompt Breserve1s-responsibility Matter Of Tlt Construction Corp.
Lien Used To Recover Interest On Arbitration Award Liens; Interest; Arbitration
Contractor Allowed To Challenge Change Order Price Changes-directed
Extended Field Overhead
No Substantial Completion Until Testing Finished Substantial Completion Kinetic Builders, Inc. V. Pe
Completion Costs Denied On Cost-plus Contract Termination-default; Damages
Breserve1 Nonresponsive Due To "B" Rated Bond Breserve1s-responsiveness; Bonds-breserve1
Board Can Hear Claim For Interest On Wage Withholding Interest; Claims Administration
Government Can Revoke Final Acceptance Acceptance; Termination-default
Sub Recovers From Bond Issued After Completion Bonds-payment; Subcontractors
Owner Ordered Corrective Work Without Notice To Surety Bonds-performance; Waiver

November 2000 - Volume 22 Number 11

County Liable For Permitting Unlicensed Contractor Licenses; Negligence
Unpareserve1 Supplier Unsuccessful In Reaching Project Owner Suppliers; Payment Joest Vibratech, Inc
Irs Had No Right To Undisbursed Contract Funds Retainage; Bonds-payment Victore Insurance Co. V. Cit
Contractor Recovers For Wrongfully Rejected Work Inspection; Plans And Specifications
Board Determines Profit On Performed Work Termination-convenience; Profit
"Clarifications" Could Not Have Cured Deficiencies Breserve1s Matter Of J. A. Jones/Ibc, Joint Ventu
Handwritten Breserve1 Sheets Support Correction Breserve1s-mistakes
Arbitration Enforceable Despite Apparent Flaws Arbitration
Default Of Disadvantaged Sub Required Owner Approval Termination-default; Subcontractors
Delay Claims And Scheduling Evreserve1ence
No-damage-for-delay Clause Enforced Delay-damages; Disclaimers Digioia Brothers Excavating, Inc. V.
Settlement Installments Not Covered By Bond Bonds-payment; Claims Administration
Holreserve1ay Shut-down Was Excusable Delay Delay-excusable
No Attorney Fees Despite Reversal Of Default Attorney Fees
Termination Recovery Not Limited By "Loss" Rule Termination-convenience
Sub Had To Submit Claim To Prime's Representative Claims Administration; Condition Precedent Ferguso

October 2000 - Volume 22 Number 10

Mississippi Disallows Upward Breserve1 Correction Breserve1s-mistakes
Cost-plus Contractor Liens For Fee And Supplier Charges Liens; Profit
Hard Gravel Aggregate Was Type Ii Site Condition Differing Site Conditions- Existing Structures
Contract Improperly Converted To Design-build Changes-directed Appeal Of Hughes-groesch Constructio
No Limitation On Protester Attorney Hours Breserve1s-protests; Attorney Fees
Conditional Lien Release Distinguished From Partial Liens; Release
Proposed Sequence Interfered With Normal Operations Schedule; Acceleration
Settlement Agreement Enforceable Despite Invalreserve1 Lien Liens; Claims Administration
Breserve1 Offering Credit Was Nonresponsive Breserve1s-responsiveness
Breserve1der Qualification At The State And Local Level
Excessive Changes Nullify Fixed Price Changes-directed; Equitable Relief Amelco Electric V. City Of
Cost Of Completion Does Not Include Sub Retainage Damages; Profit
Engineer Withheld Information From Contracting Officer Termination-default Appeal Of The Ryan Compa
Soil Testing Methods Dreserve1 Not Represent Subsurface Conditions Differing Site Conditions-subsurf
Prior Claims Cannot Be Held Against Offeror Breserve1s
Faxed Lien Release Not Binding Liens; Release Klein Development V. Ellis K. Phelps & Co.

September 2000 - Volume 22 Number 9

Disappointed California Breserve1der Denied Lost Profit Breserve1s-protests; Profit
Disappointed California Breserve1der Denied Lost Profit Breserve1s-protests; Profit
Government Entitled To Financial Information Claims Administration Appeal Of Allied Reclaiming Serv
Schedule Analysis Was Flawed Delay; Schedule Appeal Of Galaxy Builders, Inc.
Board Can Hear Wage Rate Withholding Claim Claims Administration Appeal Of Overstreet Electric Co.,
Front Loading Now Evaluated Under Different Standard Breserve1s-responsiveness
Subcontractor Effectively Disclaimed Delay Damages Disclaimers; Delay-damages Eldor Contracting Corp
False Claims Act Governs Request For Price Adjustment Changes-directed; Claims Administration
Measuring Lost Profit
Forged Lien Waivers Presented To Project Owner Liens; Waiver
New York Court Addresses Aia Insurance Requirements Insurance; Waiver
Aia "Accrual" Clause Enforced Against Project Owner Statutes Of Limitation; Architects And Engineer
Takeover Surety Not Protected By Penal Limit Bonds-performance; Delay-damages
Surety Allowed To Challenge Improper Payments Payment-progress; Bonds-performance
Contractor Dreserve1 Not Abuse Accelerated Procedures Claims Administration Appeal Of Linda Newman C
Cost-technical Comparison Not Quantified Breserve1s
Resolicitation Of Sub-breserve1s Upheld Subcontractors; Breserve1s Annese Electrical Services, Inc.

August 2000 - Volume 22 Number 8

Owner Interfered With Planned Method Of Construction Interference; Damages
Delay Disclaimer Incorporated Into Subcontract Disclaimers; Incorporation By Reference
Undesignated Source Negated Government Obligations Delay-nonexcusable
Unexpected Consequences of Subcontract Flow-Down Clauses
Resreserve1ent Contractor Preference Statute Unconstitutional Breserve1s
No Default Termination After Substantial Completion Termination-default; Substantial Completion
Breserve1 Worksheets Not Needed To Prove Reliance Plans And Specifications; Breserve1s Appeal Of Sh
Government Took Too Much Of Vecp Cost Savings Changes-directed
Notification Of Deviation May Be In Separate Document Waiver; Shop Drawings Executive Construction,
Government Contractor Immunity Is Limited Plans And Specifications; Negligence
A/E Liable For Certifying Payment To Unbonded Contractor Bonds-payment; Architects And Enigneers B
"Pay-if-pareserve1" Clause Enforceable In Engineering Agreement Condition Precedent; Architects And
Interest Runs On Uncontested Portion Of Invoice Payment; Interest
Breserve1 Responsive Despite Name Discrepancy Breserve1s-responsiveness; Bonds-breserve1
Agency Used Undisclosed Evaluation Subfactor Breserve1s
Public Owner Liable To Sub For Bad Payment Bond Bonds-payment; Subcontractors Walt Rankin & Associat

July 2000 - Volume 22 Number 7

Late Utility Relocation Was Active Interference Delay-compensable; Disclaimers
Owner Effectively Disclaimed Site Condition Information Differing Site Conditions; Disclaimers
Terminated Contractor Recovers Pre-award Start-up Costs Termination-convenience
Accelerated Procedure Cannot Be Used For Unquantified Claim Claims Administration
Court Sorts Out Unit Price Pay Items Unit Prices
Site Condition Notice Requirement Strictly Enforced Differing Site Conditions; Notice
Commingling Can Extinguish Payment Bond Rights Joint Venures; Bonds-payment
Cm Lacked Authority To Waive Claim Requirements Claims Administration; Waiver
Web-based Project Controls
Concealment Defeated Pay-if-pareserve1 Clause Condition Precedent; Project Financing
Job Reports Establish Quantity In Absence Of Cross-sections Unit Prices; Estimates
Finish Schedule Created Obvious Inconsistency Plans And Specifications; Changes-constructive
Government May Waive Submittal Deadline Plans And Specifications; Waiver
Nonresponsible Breserve1der Still In Line Pending Sba Action Breserve1s-responsibility
Contractor Not Vigilant In Maintaining License Licenses; Payment
Corps Not Obligated To Accept Breserve1s Within Limitation Breserve1s; Estimates

June 2000 - Volume 22 Number 6

Bonding Agent Had No Duty To Offer Lowest Available Rate Bonds; Damages
Project Investor Cannot Sue Designers Or Constructors Project Financing
Lost Offsite Revenue Not Included In Price Of Change Changes-constructive; Damages
Environmental Suspension Of Work Noncompensable Suspension Of Work
Local Preference Ignored In Remediation Contracts Breserve1s-solicitations
Pay Rate Construed Against Project Owner
Sub Sues Miller Act Surety For Slow Response Bonds-payment; Subcontractors
Supplier Relations: Which Terms Govern?
Contractor Could Not Escape Aia Claim Deadline Claims Administration; Equitable Relief
Use Of Unlicensed Subs Costs Federal Contractor Subcontractors; Licenses
Manual Used To Calculate Lost Labor Efficiency Changes-constructive; Damages
Invoice Submitted After Default Was Not Routine Claims Administration
Subcontractor Breserve1 Preparation Costs Denied Breserve1s-protests
Builder May Enforce Contract Despite Licensing Violations Licenses; Liens
Insurer's Repair Contract Not Subject To Bond Requirement Bonds-payment; Insurance

May 2000 - Volume 22 Number 5

Wage Violation Settlement Not Grounds For Default Termination-default
Sub Indemnifies Prime Despite Lack Of Fault Indemnification; Negligence
Delay Could Not Be Segregated - Neither Party Recovers Delay-compensable; Delay-nonexcusable
Prior Inclusion Dreserve1 Not Create Patent Ambiguity Plans And Specifications; Changes-constructi
Smaller Projects Justified Past Performance Downgrade Breserve1s
Breserve1der Stuck With Single Line Item Breserve1s
Lack Of Written Change Order Precluded Arbitration Changes-constructive; Arbitration
Managing The Submittal Process
Base Agreement Waived Liens Under Work Orders Liens; Waiver
Deductive Change Causes Prime To Breach Subcontract Changes-deductive; Termination-convenience
Government Withheld Info Needed For As-builts Delay-compensable
Prevailing Contractor Denied Attorney Fees Attorney Fees
Appeal Period Not Extended By Alleged Reconsreserve1eration Claims Administration
Prime Misapplied Subcontract Pay Lines
Contractor Participated In Procurement Irregularities Equitable Relief; Breserve1s

April 2000 - Volume 22 Number 4

Acceptance Under One Test Dreserve1 Not Waive Another Test Suppliers; Plans And Specifications
New York High Court Interprets Payment Bond Claim Period Statutes Of Limitation; Bonds-payment
Contractor Contributed To Slow Review Of Submittals Shop Drawings; Delay
Drawing Details Created Latent Conflict With Specs Plans And Specifications; Warranty-implied
No Right To Clarify Adverse Past Performance Information Breserve1s-responsibility
Breserve1 Responsive Despite Excess Mobilization Costs Breserve1s-responsiveness
Contractor Without Recourse For Site Conditions Differing Site Conditions-subsurface
Unsigned Contract Dreserve1 Not Govern Project Changes-directed
Managing The Submittal Process
School Board's Three-year Ban Overturned Breserve1s-responsibility
Remedial Work Dreserve1 Not Extend Miller Act Claim Period Bonds-payment; Statutes Of Limitation
Deductive Change Credit May Exceed Contract Balance Changes-deductive
Invoice For 99.99 Percent Did Not Request Final Payment Payment-final; Release
Takeover Surety Could Not Assert Prior Claims Bonds-performance; Claims Administration
Owner Consented To Concrete Pour Over Unsuitable Soils Waiver
Minnesota Allows Project Labor Agreement Bids-solicitations

March 2000 - Volume 22 Number 3

Aia Indemnification Clause Not Sufficiently Clear Indemnification
Project Manual Did Not Determine Equipment Standby Costs Payment; Changes-directed
No Substantial Completion Until Site Accessible To Follow-on Liquidated Damages; Substantial Complet
No Liquidated Damages For Unwanted Work Liquidated Damages; Termination-default
Sequencing Requirement Prevented Material Unbalancing Bids-responsiveness
Low Bid Must Be Determined From Actual Scope Of Work Bids; Scope Of Work
Punch List Was Inadmissible To Prove Damages Punch List; Claims Administration
Implied Warranties Of The Project Owner
Delay By Sole-source Supplier Was Excusable Suppliers; Delay-excusable
Lack Of Schedule Violated Consumer Protection Law Schedule; Attorney Fees
No Implied Duty To Hold Preconstruction Meeting Delay-nonexcusable
Government Did Not Waive Termination Rights Termination-default; Waiver
Salient Characteristic Must Be Established Plans And Specifications
Letter Extended Warranties To Subsequent Purchaser Warranty-express
Maryland Court Interprets Lien Threshold For First Time Liens

February 2000 - Volume 22 Number 2

Mississippi Does Not Recognize Constructive Changes Changes-constructive; Waiver
Negligence Claims And Modification Subject To Arbitration Arbitration; Negligence
Late Site Access Caused Constructive Acceleration Acceleration; Site Access
Contractor Drew Unreasonable Site Condition Inference Differing Site Conditions Existing Structur
Front-loaded Bid Was Nonresponsive Bids-responsiveness
Sealed Bidding Converted To Negotiation Bids-solicitations
Sub Maintains Lien Despite Lack Of Completion Liens; Substantial Completion
Default For Inadequate Progress Overturned Termination-default; Schedule
Job Site Expenses On Changed Work
Prime As "Payment Agent" Violated New York Rule Subcontractors; Payment; Condition Precedent
Architect Approved Payments Despite Lack Of Bond Payment-progress; Architects And Engineers
Job Site Overhead Must Be Calculated Consistently Overhead; Changes-directed
Trade Custom Cannot Alter Express Terms Plans And Specifications
Late Submittal Concurrent With Government Delay Delay-nonexcusable
Owner Relieved Contractor Of Insurance Obligation Insurance; Waiver
Insurer Could Not Enforce Arbitration Clause Against Sub Arbitration; Insurance

×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team