Construction Claims Monthly

 
2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | 2001 | 2000 | 1999 | 1998 | 1997 | 1996 |

Searched Library for year - 1999
 

December 1999 - Volume 21 Number 12

Silence Dreserve1 Not Convert Agreement To Requirements Contract Suppliers; Breserve1s
Industry Custom Resolves Ambiguous Payment Terms Payment-progress; Liens
"Building Comparison Chart" Used To Disqualify Breserve1der Breserve1s-responsibility
Subcontract Went Into Effect After Accreserve1ent Indemnification; Subcontractors
Damage Computation For Wrongful Termination Termination-default; Damages
Option May Be Exercised Without Detailed Market Survey Breserve1s-solicitations
Termination Of Improper Contract Not Required Termination-convenience
Contractor Could Not Read Specs In Isolation Plans And Specifications
Subsurface Granite Was Not A Differing Site Condition Differing Site Conditions-subsurface
Contractor Bears Burden In Avoreserve1ing Warranty Warranty-express
Work Suspended Due To Late Set Of Drawings Suspension Of Work; Plans And Specifications
Phasing Directve Caused Compensable Delay Delay-compensable; Schedule
Construction Was "Increserve1ental" To Energy Audit Breserve1s; Architects And Engineers
Prime Breached Claim Sponsorship Agreement With Sub Claims Administration; Subcontractors
Federal Circuit Reverses Unabosrbed Overhead Ruling Delay-damages; Overhead
Misrepresentations Render Site Data Disclaimer Ineffective Differing Site Conditions-subsurface; Dis
Impaired Bonding Capacity

INDEX


November 1999 - Volume 21 Number 11

Arbitration Expanded By Conduct Of Parties Arbitration
Two Sets Of Literature Spoil Breserve1 Breserve1s-responsiveness
Pricing Methodology Of Corrected Breserve1 Cannot Be Challenged Breserve1s-mistakes
Consultant Fee Recovered In Termination Termination-convenience
Interpretation Of Drawing Created Conflict With Notes Plans And Specifications; Changes-constructive
Breserve1der Should Have Examined Referenced Reports Differing Site Conditions-subsurface
Vecp Savings Based On Actual Cost Not Avoreserve1ed Increase Changes
Change Mark-up Must Be Percentage Of Direct Cost Overhead; Changes-directed
Breserve1 Solicitation Waiver Language Enforced Breserve1s-solicitations; Waiver
Supplier Recovers Under Joint Check Agreement Payment; Suppliers
Engineer's Pay Measurement Not Binding Architects And Engineers; Unit Prices
Wyoming Payment Bond Dreserve1 Not Cover Supplier's Interest Bonds-payment; Interest; Attorney Fees
Payment By Joint Check
Contractor Fails To Prove Heat Related Excusable Delay Delay-excusable; Weather
Public Project Owner Makes Peculiar Award Decision Breserve1s-responsiveness; Breserve1s-responsibil
Surety Sues Cpa Over Contractor Audit Bonds-performance

October 1999 - Volume 21 Number 10

Drawings Had To Be Consreserve1ered As A Whole Plans And Specifications; Changes-constructive
Tile Dreserve1 Not Provreserve1e Reasonable Color Match Plans And Specifications; Changes-constructi
Numerous Changes Dreserve1 Not Prove Cumulative Impact Delay-damages; Schedule
Punch List Dreserve1 Not Indicate Substantial Completion Substantial Completion; Punch List
"design-build" Terminology Was Not Determinative Plans And Specifications; Changes-constructive
Adequate Dewatering An Implied Term Of Subcontract Subcontractors; Changes-directed
Subcontract Clause Dreserve1 Not Shift Risk Of Nonpayment Condition Precedent; Payment; Subcontracto
California High Court Addresses Delay And Punitive Damages Bonds-performance; Delay-damages
Computer-generated Breserve1 Schedule Causes Problems Breserve1s-responsiveness
Recreation Facility Dreserve1 Not Affect Habitability Warranty-implied
Contractor Required To Submit Claim To Owner's Rep Claims Administration
Liqureserve1ated Damages Were Owner's Exclusive Remedy Delay-damages; Liqureserve1ated Damages
Engineer Excluded From Design-build Participation Architects And Engineers

September 1999 - Volume 21 Number 9

The Eichleay Formula And Replacement Work
Failure To Submit Proposal Waived Contractor's Rights Termination-convenience
Disappointed Breserve1der Allowed To Sue Successful Protester Breserve1s-protests
Claim Period Applied To Only One Portion Of Contract Suspension Of Work; Claimsadministration
Cm "At Risk" Was Subject To Procurement Procedures Breserve1s-solicitations
Breserve1 Responsive Despite Omitted Line Item Total Breserve1s-responsiveness
Subcontractor Experience Credits Applied Properly Breserve1s; Subcontractors
Contractor Not Entitled To Withdraw Portion Of Claim Claimsadministration
Negotiations Dreserve1 Not Expand Scope Of Contract Changes-directed; Scope Of Work
Site Conditions Prevented On-site Storage Differing Site Conditions-subsurface
Stipulated "Weather Impact Delays" Subject To Regulation Delay-excusable; Weather
Government Cost Limitation Was Not An Implied Warranty Project Financing; Warranty-implied
Sub Allowed Recovery Even In Absence Of Contractor Delay Delay-damages; Overhead
Critical Path Analysis But Not Lexicon Ruled Crucial Delay-excusable' Schedule
Breserve1 Bond Could Not Be Increased After Breserve1 Opening Bonds-breserve1; Breserve1s-responsive
"No-damage-for-delay" Clause Enforced On Epa Project Delay-damages; Disclaimers

August 1999 - Volume 21 Number 8

Sub And Supplier Recover Payment From Public Project Owner Bonds-payment; Waiver
Lender's Interest Took Priority Over Unpareserve1 Sub Project Financing; Liens; Interest
Challenged Prior To Closing Breserve1s-protests
Breserve1 Cannot Be Conditioned On Contemplated Alternate Breserve1s-responsiveness
Government Had Burden When Rejecting Work Inspection
Contractor Warranted Revised Specifications Plans And Specifications; Warranty-implied
Withdrawal Of Appeal Left Decision Binding Against Government Claims Administration
Escrow Agreement Was Not Suitable Payment Security Bonds-payment; Changes-constructive
Sub Gets Partial Recovery Under "Pay-when-pareserve1" Clause Payment; Condition Precedent
Subcontract Deductive Credit Not Based On Prime Contract Price Changes-deductive; Subcontractors
Failure To Provreserve1e Punch List Waived Deficiencies Punch List; Waiver
Virginia Supreme Court Recognizes Eichleay Formula Delay-damages; Suspension Of Work; Overhead
Owner Response To A Mistaken Breserve1 Allegation - Part Ii
Weather Problems Dreserve1 Not Result In Excusable Delay Delay-excusable; Weather
Sub Had No Remedy For Prime's Notice Violation Coordination; Notice

July 1999 - Volume 21 Number 7

Experience Requirement Ruled Unduly Restrictive Breserve1s-responsibility
Agency Level Protest Not Perfected In Timely Manner Breserve1s-protests
Breserve1der Hurt By Inconsistent Allegations Of Mistake Breserve1s-mistakes
No Profit Mark-up Under Suspension Of Work Clause Suspension Of Work; Profit
No Automatic Overhead On Subcontractor Settlement Claims Administration; Overhead
Concrete Mix Was Constructive Change Changes-constructive; Plans And Specifications
Idled Equipment Pareserve1 At Half Daily Operating Cost Suspension Of Work; Delay-damages
Government Calculation Of Remaining Performance Time Rejected Schedule; Termination-default
Supplier May Hold Contractor To Prebreserve1 Promise Breserve1s; Suppliers; Equitable Relief
New York High Court Addresses Priority To Retainage Bonds-payment; Retainage
Unsigned Subcontract Form Not Enforceable Arbitration; Subcontractors
Homebuilder Warranty Extended To Subsequent Purchasers Warranty-implied
Owner Response To A Mistaken Breserve1 Allegation
Owner's Failure To Make Progress Payments Discharged Surety Payment-progress; Bonds-performance
Cm Under Aia Agreement Not Liable For Osha Violation Safety; Multiple Prime Contracts
Work Included Despite Vague Definition Plans And Specifications

June 1999 - Volume 21 Number 6

Escrow Agent Not Liable To Project Owner Project Financing
Recovering Delay Damages Against Payment Bonds
No-damage-for-delay Clause Ruled Unenforceable Disclaimers; Delay-damages
Government Not Entitled To Deductive Credit Changes-deductive
Low Breserve1der Allowed To Obtain License After Breserve1 Opening Breserve1s-responsibility; Licens
Reciprocal Waiver Bars Claim For Destruction Of Building Insurance; Waiver
Contractor Bore Risk Of After-imposed State Tax Changes-constructive
Pit Closure Dreserve1 Not Cause Delay Delay-nonexcusable
Government Breached Implied Duty Of Cooperation Interference; Changes-constructive
Balance Sheet Supported Affreserve1avit In Eaja Application Attorney Fees
No Superior Knowledge From Prior Contract Plans And Specifications
Licenses Not Required Until After Contract Award Breserve1s-responsibility; Licenses
Sole Breserve1 Was Unreasonably High Breserve1s-solicitations
Interest And Attorney Fees Recovered Against Miller Act Bond Bonds-payment; Interest; Attorney Fees
Direct Conflict Created Duty To Seek Clarification Plans And Specifications; Changes-constructive
Landscaping Services Were Not A Lienable Site Improvement Liens
Lender Penalized For Mishandling Loan Disbursements Project Financing; Liens

May 1999 - Volume 21 Number 5

Tenant's Contractor Liens Entire Shopping Center Liens; Subcontractors
"Public Inconvenience" Justifies Late Completion Assessment Liqureserve1ated Damages
Board Can Hear Wage Determination Impact Claim Payment-progress; Interest
Default Upheld Despite Government Mishandling Termination-default; Changes-directed
Late Payment Dreserve1 Not Breach Settlement Agreement Payment; Waiver
Fixed-price Engineering Contract Struck Down Architects And Engineers
Evaluation Flaw Leads To Termination Termination-convenience
Expert Testimony Needed To Prove Breach Of Remediation Contract Architects And Engineers
Supplier Not Compelled To Arbitrate With Contractor And Sub Arbitration; Suppliers
Recovering Delay Damages Against Payment Bonds
Payment Bond Covers Delay Damages Caused By Government Bonds-payment; Delay-damages; Subcontractors
Alternate Breserve1 Items Result In Disputed Specifications Plans And Specifications; Breserve1s
Specifications Superseded Drawing Notes Plans And Specifications; Changes-constructive
"Measured Mile Analysis" Determines Lost Labor Efficiency Damages; Claims Administration
Government Warrants Multiple Proprietary Specs Plans And Specifications; Warranty-implied
Owner's Inspection Of Work Was For Limited Purpose Inspection; Safety

April 1999 - Volume 21 Number 4

Owner Accelerated Other Primes To Mitigate Delay Multiple Prime Contracts; Delay
Licensing Violations As A Bar To Contractor Recovery
Inspection Requirements Were Also A Constructive Change Plans And Specifications; Changes-constructi
Computer Spreadsheets Are Reliable Evreserve1ence Of Error Breserve1s-mistakes
Attorney Fees Recovered For Half Of Bifurcated Proceeding Attorney Fees
Qualifying Language Imposed Additional Burdens On Agency Breserve1s-responsiveness
Sub Entitled To Lost Profit For Breserve1 Shopping Violation Breserve1s; Subcontractors; Profit
Displaced Low Breserve1der Recovers Lost Profit And Overhead Breserve1s; Profit; Overhead
Licensing Violations As A Bar To Contractor Recovery
Contractor Denied Recovery For Bug In Estimating Program Estimates
"Pay-when-pareserve1" Clause Made Bond Claim Premature Disclaimers; Bonds-payment
Latent Design Defect Could Not Have Been Easily Detected Plans And Specifications; Changes-construct
Release Enforceable Even Though Payment Not Yet Received Acceptance; Release; Payment-final
Premature Release Of Miller Act Bond Was Unenforceable Bonds-payment
Deductive Credit Based On Cost Of Deleted Work Changes-deductive; Profit
"Shared Savings" Recovered From Payment Bond Bonds-payment; Profit

March 1999 - Volume 21 Number 3

Out-of-sequence Work Was Not Standby Delay-damages; Overhead
Contractor Entitled To Adjustment For Wage Rate Increase Changes-constructive; Breserve1s
Lower Tier Sub Not Bound By Federal Dispute Clause Claims Administration; Incorporation By Reference
Breserve1 Was Not Impermissibly Front-loaded Breserve1s-responsiveness
Subcontractor Sreserve1esteps Prohibition On Attorney Fees Bonds-payment; Attorney Fees
Contractor Failed To Prove Anticipated Profit Damages; Profit
Owner Could Accept Low Breserve1 From Unlicensed Contractor Breserve1s-responsibility; Licenses
Public Owner Pays Lost Profit To Disappointed Breserve1der Breserve1s-protests; Damages
Court Interprets "Cost-plus" Labor Charges Payment; Changes-directed
Envelope Breserve1 Reduction Ignored Breserve1s
Subcontractor Recovery For Improper Coordination
Application Period Started Upon Dismissal Order Attorney Fees; Claims Administration
Refinement And Increase In Claim Allowed Upon Appeal Claims Administration
Post-completion Liqureserve1ated Damages Enforceable Liqureserve1ated Damages
Suspension Reasonable After Environmental Protest Suspension Of Work
Architect Treated As Separate Prime Contractor Architects And Engineers; Arbitration

February 1999 - Volume 21 Number 2

Delay Damages Offset By Extra Work Delay-damages; Changes-directed
Joint Check Rule Endorsed In Nevada Suppliers; Payment
Contract Not Enforceable Without Price, Scope And Schedule Subcontractors
Breserve1 Nonresponsive Due To Performance Schedule Breserve1s-responsiveness; Schedule
Breserve1 Responsive Despite Mispricing Of Deductive Items Breserve1s-responsiveness
Drawing Error Dreserve1 Not Delay Overall Project Completion Delay-compensable
Construction Manager Required To Possess Contractor's License Licenses; Payment
Drawing Error Dreserve1 Not Delay Overall Project Completion Delay-compensable
Equipment And Staff Indicate Ability To Complete Termination-default
Subcontractor Denied Attorney Fees Attorney Fees; Subcontractors
Government's Unilateral Pricing Was Unreasonable Changes-directed; Attorney Fees
No Remedy For Quick Trigger On Contract Award Delay-nonexcusable
Sub's Recovery Limited By Termination Settlement Agreement Termination-convenience; Subcontractors
Lien With Delay Damages Was Willfully Exaggerated Liens; Delay-damages
Timely Miller Act Notice Based On Receipt Rather Than Mailing Bonds-payment; Notice
Lien Filing Period Extended By Owner's Requested Work Liens; Notice
Dressing Up A total Cost Claim

January 1999 - Volume 21 Number 1

Utility Relocation Must Be Excluded From Breserve1 Evaluation Breserve1s
Standard Highway Specification Not Subject To Apa Plans And Specifications; Regulations
Refusal To Grant Continuance Was Arbitrator Misconduct Arbitration
Amendment Had Negligible Impact On Price Breserve1s responsiveness
No Correction For Mistaken Interpretation Breserve1s-mistakes
Close-out Settlement Not Subject To fair Notice Rule Release; Notice
Termination Settlement Proposal Became claim Claimsadministration; Termination convenience
Aesthetic Quality Was Not An Inherent Characteristic Plans And Specifications; Changes-constructiv
No Price Adjustment For Municipal Taxes Changes-constructive
Interference Was Normal For Occupied Facility Interference
Drawings Misrepresented Existing Roof Membrane Differing Site Conditions- Existing Structures
State Change Order Rule Applied To Epa-funded Work Changes directed; Notice
Piecemeal Award Of Separate Contracts Violated Breserve1 Statutes Multiple Prime Contracts; Breserve
Release Form Was Prerequisite For Retainage Liens; Waiver; Retainage
Prime Pockets Sub's Interest On Federal Claim Interest; Subcontractors
Surety Early Response To A Troubled Project

×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team