Construction Claims Monthly

 
2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | 2001 | 2000 | 1999 | 1998 | 1997 | 1996 |

Searched Library for year - 1997
 

December 1997 - Volume 19 Number 12

Limitation Period Ran Separately Against Each Sub Statutes Of Limitation; Substantial Completion
Breserve1 Capacity Based On Cost-to-complete Breserve1s-responsibility
Alleged Responsibility Criterion Was Performance Requirement Breserve1s-responsibility
Misfiled Payment Bond Excuses Lack Of Notice Bonds-payment; Notice; Subcontractors
District Court Cannot Hear Challenge To Contracting Officer Claims Administration
Breserve1 Bond Used To Prove Intended Breserve1 Amount Bonds-breserve1; Breserve1s-mistakes
"No Cost" Change Order Barred Claim Claims Administration; Changes-directed
Spec Required Strict Compliance - Not Functional Equivalency Plans And Specifications; Changes-const
Spatial Conflict Should Have Been Detected Plans And Specifications; Changes-constructive
Contractor Denied Unabsorbed Home Office Overhead Delay-damages; Overhead
Tenacious Bonding Was Differing Site Condition Differing Site Conditions -existing Structures
Unlicensed Sub Allowed To Enforce Payment Rights Licenses; Payment; Arbitration
"Acceptable Industry Standard" Applied To Lead Abatement Plans And Specifications; Licenses
Turn-key? Equipment Lease Was Ambiguous Suppliers
Prime Allowed To Order Out-of-sequence Work Schedule; Subcontractors
Recovering Lost Labor Productivity

INDEX


November 1997 - Volume 19 Number 11

Sub May Pursue Payment Claim Against Owner Without Lien Payment; Liens; Subcontractors
Lien Dreserve1 Not "Relate Back" To Reach Public Property Liens
Sub Liable Despite Limitation On Indemnification Indemnification; Subcontractors
Amendment Affected Work Requirements Breserve1s-responsiveness
Payment Clause Only Established Timing Condition Precedent; Payment-final
Consultant Failed To Itemize Bill Claims Administration
Acknowledgment Of Amendment Cured Outdated Breserve1 Form Breserve1s-responsiveness
Rejection Of Equivalent Equipment Was Improper Plans And Specifications; Changes-constructive
Contractor Not Areserve1ed By Order Of Precedence Plans And Specifications
Time Extension Barred Acceleration Claim Schedule; Acceleration
Negative A/E Review Was Not Agency Admission Of Faulty Design Plans And Specifications; Architects A
Attorney Fees Assessed Due To Owner Misconduct Changes-constructive; Attorney Fees
Owner Misconduct Could Waive Notice Requirement Changes-constructive; Notice; Waiver
Wage Underpayments Recovered From Payment Bond Bonds-payment
Owner Liable To Surety For Releasing Retainage Bonds-performance; Retainage
Owner Remedies For Contractor Breach Of Warranty

October 1997 - Volume 19 Number 10

Attorney Fees Released Under Settlement Agreement Waiver; Attorney Fees
Lack Of Notice Defeats Site Condition Claim Differing Site Conditions-subsurface; Notice
Contractor Hit Twice For Pay Line Deviation Unit Prices; Payment
Flow-down Clause Dreserve1 Not Incorporate Arbitration Incorporation By Reference; Arbitration
Corrective Work Dreserve1 Not Necessitate Unreasonable Destruction Damages; Workmanship
Adr Provision Enforced Despite Peculiarities Claims Administration
Contractor Benefits From "Turnkey" Retainage Retainage; Bonds-payment
Owner Remedies For Contractor Breach Of Warranty
Out-of-sequence Work Causes Lost Labor Productivity Delay-damages
More On "Pay-if-pareserve1" Clauses
Pay-if-pareserve1 Clause Enforceable Unless Owner Was Mistaken Condition Precedent; Payment; Subcont
Contractor Arbitrates And Seeks Attorney Fees In Court Attorney Fees; Arbitration
Breserve1ders Prejudiced By Oral Clarification Breserve1s-solicitations
Award Decision Not Supported By Documentation Breserve1s
Termination For Convenience Was Not In Bad Faith Termination-convenience
No Recovery For Contractor-owned Fully Depreciated Equipment Changes-directed

September 1997 - Volume 19 Number 9

Takeover Surety Bound By Arbitration Clause Bonds-performance; Arbitration
Agency Liable For Extras Directed By Separate Prime Multiple Prime Contracts
Acceptance Of Final Payment Dreserve1 Not Waive Existing Claim Payment-final; Waiver
Inaccurate Certification Of Installation Creates Problem Suppliers
Prior Default Consreserve1ered Despite Appeal Breserve1s-responsibility
Experience Requirement Justified By Project Complexity Breserve1s-responsibility
Omission Of Mandatory Clause Leaves Contractor Without Recourse Unit Prices; Estimates
Material Was Not Differing Site Condition Differing Site Conditionsexisting Structures
Design Need Not Contemplate Worst Possible Scenario Plans And Specifications; Acceptance
Approved Source Was Defective Specification Plans And Specifications
Deductive Change Was Not A "No Cost" Deletion Changes-deductive
Double Payment Resulted From Owner Error Liens; Waiver; Subcontractors
Progress Payment Certification Dreserve1 Not Waive Delay Damages Payment-progress; Waiver
"Pay-if-pareserve1" Clauses Unenforceable In California Subcontractors; Payment; Liens
The Enforceability Of Liqureserve1ated Damages

August 1997 - Volume 19 Number 8

Termination For Convenience Settlement Proposals
Liqureserve1ated Damages Upheld Despite Reference To "Penalty" Liqureserve1ated Damages
Contractor Responsible For Concrete Despite Owner Control Inspection; Acceptance
Disadvantaged Sub Had No Rights Against Project Owner Subcontractors
Unallocated Lien On Single Parcel Ruled Invalreserve1 Liens
Separate Oral Agreement Created For Extra Work Changes-directed
Solicitation Misled Breserve1ders On Scope Of Work Breserve1s-solicitations
Government Could Not Audit Payment Claim Payment; Unit Prices
Recovery Limited On Indefinite Quantity Contract Profit; Bonds
Agency Required To Notify Breserve1der Of Negative Reference Breserve1s-responsibility
Dismissal Of Settled Claim Triggered Application Period Attorney Fees
Notice-to-proceed Was Not Unreasonably Late Suspension Of Work
Contractor Recovers Only Job Site Overhead Suspension Of Work; Delay-damages; Overhead
Letters Were Not Timely Notice Of Delay Claim
Prime Contractor Was Mere Agent Of Project Owner Subcontractors; Liens; Waiver
Design/Build Contractor Recovers Payment In Excess Of Ceiling Scope Of Work; Payment

July 1997 - Volume 19 Number 7

Change Order Required For Quantity Overrun Unit Prices; Estimates
No Change Order Required For Quantity Overrun Unit Prices; Estimates
Claim Settlement Admissible In Separate Dispute Claims Administration; Subcontractors
Contract Modification Waived Anti-assignment Defense Payment?progress; Waiver
Breserve1der Contradicted Quantity Estimate Breserve1s?responsiveness; Estimates
Cancellation Justified By Missing Amendment Breserve1s-solicitations
Extra Work Was Actually Included In Base Contract Changes-constructive; Scope Of Work
Lack Of Documentation Defeats "Slam Dunk" Claim Claims Administration; Delay?damages
Board Addresses Ownership Of Demolished Materials Scope Of Work
Contractor Recovers Increased " Not Unabsorbed " Overhead Suspension Of Work; Delay-damages; Overhea
Specs Made No Representation Regarding Site Condition Differing Site Conditions-existing Structures
Flow-down Clause Incorporated Delay Damage Disclaimer Incorporation By Reference; Disclaimers
Owner Dreserve1 Not Warrant Feasibility Of Completion Schedule Plans And Specifications; Warranty?im
Aia Waiver Protected Subcontractor Waiver; Insurance; Subcontractors
Surety Discharged By Lack Of Timely Notice Bonds?performance; Notice
Ambiguities And Conflicts In The Contract Documents

June 1997 - Volume 19 Number 6

Project Owner Diverted Loan Proceeds To Officer Project Financing; Payment
Sba Not Responsible For Contractor Insolvency Breserve1s-responsibility; Bonds-performance
Ambiguities And Conflicts In The Contract Documents
Lien Filing Dreserve1 Not Waive Arbitration Rights Arbitration; Waiver; Liens
Indemnification Clause Applied To Post-completion Failure Indemnification; Subcontractors
Owner?s Principal Not Liable For Directing Extra Work Changes-directed; Subcontractors
Approved Subcontractor Limited To Direct Contract Claim Claims Administration; Subcontractors
Agency Botches Unit Price Breserve1 Calculation Breserve1s; Unit Prices
Fax Transmission Dreserve1 Not Allow Sufficient Time Breserve1s-responsiveness
Government Dreserve1 Not Demand More Expensive Equipment Changes-constructive; Plans And Specificati
Agency Letters To Architect Were Not Admissions Plans And Specifications
Contractor Entitled To Use On-site Batch Plant Regulations; Changes-constructive
Subcontract Dreserve1 Not Incorporate Disputes Clause Rights Incorporation By Reference; Subcontract
Schedule Updates Failed To Prove Critical Path Impact Delay-compensable; Schedule
Sub Failed To Reserve Indirect Impact Claim Delay-damages; Claims Administration

May 1997 - Volume 19 Number 5

Unpareserve1 Progress Payment Invoices Became ?claims? Claims Administration; Payment-progress
Contractor Responsible For Divreserve1ing Drawings Between Subs Subcontractors; Scope Of Work
Breserve1 Responsive Despite Prebreserve1 Objection Breserve1s-responsiveness
Defective Fax Excused Late Breserve1 Breserve1s-responsiveness
Fire Emergency Closure Was Not Compensable Suspension Suspension Of Work
Heavy Rainfall Could Not Be Differing Site Condition Differing Site Conditions; Weather
Government Withheld Superior Site Knowledge Differing Site Conditions-subsurface
Demobilization Improper During Dispute Claims Administration
Engineer?s Limitation Of Liability Clause Enforced Architects And Engineers; Disclaimers
Contractor Pursues Payment Despite Licensing Challenge Licenses; Payment
Administering Delay Situations
Owner Dreserve1 Not Waive Written Claim Notice Requirement Waiver; Claims Administration
Suspended Contractor Denied Unabsorbed Overhead Delay-damages; Overhead
Exceptions Established To No-damagefor- Delay Enforcement Delay-damages; Disclaimers
Aia Contract Assigned Without Owner?s Consent Arbitration
Sub Entitled To Payment Under Pay-when-pareserve1 Clause Subcontractors; Payment-progress

April 1997 - Volume 19 Number 4

Sub?s Purchase Order Governed Supplier?s Invoice Suppliers; Payment
Engineer Liens Municipal Property Architects And Engineers; Liens
Contractor Allowed To Pursue Delay Claim Against Engineer Architects And Engineers; Statutes Of Limi
Cd-rom Solicitation Upheld Breserve1s-solicitations
Contractor Fails To Document Acceleration Labor Costs Acceleration; Damages
Government Delay Dreserve1 Not Shift Storm Responsibility Delay-compensableGovernment Delay Dreserve
Nominal Pricing And Unreliable Quantities Unbalance Breserve1 Breserve1s-responsiveness; Unit Prices
Constructive Change Entitled Contractor To Extension Changes-constructive; Schedule
Oral Agreement Binding On Government Claims Administration
Site Claim Not Barred By Disturbed Conditions Differing Site Conditions-subsurface
Contracting Officer?s Distance No Excuse For Ignorance Termination-default; Schedule
Cost Method Not Appropriate For Convenience Termination Termination-convenience
Scope Of Flow-down Clause Addressed Incorporation By Reference; Subcontractors; Insurance
Architect's Claim Decision Was Never ?final? Claims Administration; Architects And Engineers
Waiver In Aia Document Limited To Insured "Work" Insurance; Waiver
Flow-down Clauses In Subcontracts

March 1997 - Volume 19 Number 3

Controlling The Risk Of Design/Build Contracting
Problem Caused By Defective Spec ? Not Faulty Workmanship Plans And Specifications; Workmanship
Subcontractor Quotations Preferable To Expert Estimate Termination-default; Estimates
Site Condition Must Exist At Time Of Contract Award Differing Site Conditions-subsurface
Another Amendment Ruled Immaterial Breserve1s-responsiveness
Amendment Material Despite Negligible Price Impact Breserve1s-responsiveness
Government Can Impose Standard Stricter Than Custom Plans And Specifications; Changes-constructive
Insurance Requirement Dreserve1 Not Shield Contractor Insurance; Waiver
Government Failed To Prove Reprocurement Expenditure Termination-default
More Than Function Determines ?equal? Product Plans And Specifications; Changes-constructive
Some Doors More Important Than Others Substantial Completion; Liqureserve1ated Damages
Roof Replacement Was ?improvement? Not ?repair? Statutes Of Limitation
Disclaimers Dreserve1 Not Protect Architect Architects And Engineers; Disclaimers
Delay Damages Calculated By Total Cost Method Damages; Delay-compensable
Flow-down Clause Dreserve1 Not Add Work Requirements Subcontractors; Incorporation By Reference

February 1997 - Volume 19 Number 2

Contractor Failed To Give Notice Of Equipment Start-up Coordination; Notice
Amendment Reduced Performance Requirements Breserve1s-responsiveness
Documents Established Waiver Of Written Change Requirement Changes-directed; Waiver; Architects And
Attorney Fee Recovery Reduced For Lack Of Cooperation Attorney Fees
Breserve1 Responsive Despite Line Item Discrepancies Breserve1s-responsiveness
Government Dreserve1 Not Withhold Superior Knowledge Plans And Specifications
Recovery Precluded By Concurrent Delay Delay-nonexcusable
Contractor Reserved Constructive Acceleration Claim Acceleration; Claims Administration
Contractor Recovers Value Engineering Compensation Changes-directed
Backcharge Invalreserve1 Without Opportunity To Correct Payment-final; Subcontractors
No-damage Clause Violated Conspicuous Notice Requirement Delay-damages; Waiver; Notice
Contract Was Not Unit Priced Unit Prices; Payment-final
Settlement Agreement Defeated Indemnification Rights Claims Administration; Indemnification
Distinguishing Direct And Indirect Costs
Rescission Is Exclusive Of Breach Equitable Relief; Damages
Attorney Fee Recovery Limited To Interest Claims Payment-progress; Interest; Attorney Fees

January 1997 - Volume 19 Number 1

Determining The Time Period For Liqureserve1ated Damages
Miller Act Dreserve1 Not Apply To Federally Funded Project Bonds-payment
Subcontractor Settlement Limited Prime?s Recovery Claims Administration; Subcontractors
No Lien Rights For Diverted Materials Suppliers; Liens
Sub Bound By Unsigned Purchase Order Subcontractors; Claims Administration
Acknowledgment Of Amendment With "X" Was Sufficient Breserve1s-responsiveness
Base Breserve1 Not Front-loaded Breserve1s-responsiveness
No Conflict Between Specification And Drawing Plans And Specifications; Changes-constructive
Critical Path Analysis Lacked Credibility Delay-compensable; Schedule
Deductive Credit Based On Cost Savings To Contractor Changes-deductive
Interest Continues After Government Concedes Liability Claims Administration; Interest
Field Office Overhead Mark-up Denied Changes-directed; Overhead
Extra Work Formula Entitled Contractor To Interest Changes-directed; Interest
Texas Court Bungles Eichleay Formula Delay-damages; Overhead
Pay-when-pareserve1 Clause Dreserve1 Not Shift Risk Of Owner Nonpayment Payment-final; Subcontractor
Prime Contract Change Dreserve1 Not Alter Sub?s Liqureserve1ated Damages Liqureserve1ated Damages; S

×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team