Construction Claims Monthly

 
2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | 2001 | 2000 | 1999 | 1998 | 1997 | 1996 |
 

April 2017 - Volume 39 Number 4

 
Omitted F.A.R. Bond Provision Was Nonetheless Part Of Contract
5-Year Statute Of Repose Protected Roofing Supplier
Accord & Satisfaction Didn't Release Recovery Rights For Latent Defects
FEDERAL CASES: Contractor Underbid Hazardous Waste Work---At Its Own Risk
Contract Contained 2 Different Payment Schemes For Concrete Work
Order Of Precedence Clause Negated Drawings' Direction
BID PROTESTS: Technical Superiority Legitimately Outweighed $100K Additional Contract Cost

March 2017 - Volume 39 Number 3

 
Arbitrator Reached Beyond Contract's Termination Terms
Contractor Doesn't Owe Amounts It Never Received From Delay-Causing Owner
Sub Had No Hand In And No Liability For Injury
FEDERAL CASES: Owner Released Sub's Rights To Delay Damages
Possibility Of Subsurface Condition Was 'Obvious' And 'Apparent'
'Broad Exculpatory' Clauses Didn't Stop Differing Conditions Claim

February 2017 - Volume 39 Number 2

 
Owner To Pay $20M For Messing With Contractor's Means & Methods---Despite No-Damages Clause
No Bad Faith Where Surety's Interests Aligned With Contractor's
Safety Violation Was A 'Material' Breach
FEDERAL CASES: Contract's Definition Of 'The Dispute' Was Up For Dispute
Contractor's Interpretation Of Static Site Conditions Was Unfounded
BID PROTESTS: No 'Spoon-Feeding' Of Discussion Question Responses

January 2017 - Volume 39 Number 1

 
Contractor Had Exclusive Right To Serve Govt.'s Paving Needs
Contractor's Entitlement To $1M Extra Pay Depends On 'Fill' Definition
Court Demands Clarification Of Ambiguous Arbitration Award
Sureties Can't Compel Unpaid Designer To Arbitrate
Direct V. Consequential Damages Distinction Depends On Time
FEDERAL CASES: Govt. Must Retract 53 Days Of Liquidated Damages
BID PROTESTS: 'Task Orders' Are Not Necessarily 'Contracts'